Borders General Hospital
G2 were awarded the contract to replace the air conditioning at Borders General Hospital after submitting a successful tender .
The scope of works was to completely replace and renew the air conditioning in the server room for I.T department consisting of Mitsubishi wal mounted units
This was a tricky installation. The servers in this area could not be isolated as they are the main hub for a large part of the NHS network.
This meant critical and careful planning to mitigate risk from servers overheating and also from dust and damage etc.
If these servers did over heat and crash it would have had catastrophic consequences
A staggered approach was utilised and we fully replaced and got operational one system at a time.
This project showcases G2’s ability to communicate , plan and execute correctly to achieve an excellent end result.